Page 1 of 1

Length of time for AHK to connect net metering system

Posted: Mon Aug 22, 2022 4:42 pm
by kansas
Our photovoltaic panels were installed a while ago, but nobody appears to know how long it will take for AHK to come to inspect and connect.

Anybody else in the same situation?

Re: Length of time for AHK to connect net metering system

Posted: Mon Aug 22, 2022 5:46 pm
by Devil
I informed the EAC that the panels were ready and installed on 22 May. Nothing has been heard since, despite my reminders.

Re: Length of time for AHK to connect net metering system

Posted: Mon Aug 22, 2022 6:26 pm
by trevnhil
I am puzzled that some people are waiting for EAC and others are waiting for AHK ??

Re: Length of time for AHK to connect net metering system

Posted: Mon Aug 22, 2022 6:45 pm
by kansas
I thought the same, trevnhil, but apparently AHK appears on the bill and it's their logo on their vans and buildings in Greek, but I much prefer EAC!

Re: Length of time for AHK to connect net metering system

Posted: Mon Aug 22, 2022 6:56 pm
by cyprusmax47
trevnhil wrote: Mon Aug 22, 2022 6:26 pm I am puzzled that some people are waiting for EAC and others are waiting for AHK ??
AHK is Greek (archi hlectrismou kyprou) while EAC is English (Electricity Authority of Cyprus)

Max

Re: Length of time for AHK to connect net metering system

Posted: Mon Aug 22, 2022 7:03 pm
by cyprusmax47
Back to the topic: As the supplier has also to be present when EAC comes to connect a net metering system, the month August with companies having holidays as well as EAC personal, not much will happen....but soon comes September ;) siga siga

Max

Re: Length of time for AHK to connect net metering system

Posted: Mon Aug 22, 2022 8:28 pm
by kansas
Cyprusmax47 I think it will be November or December siga siga We'll get them to switch on our Christmas lights while they're here!!!

Re: Length of time for AHK to connect net metering system

Posted: Mon Aug 22, 2022 11:27 pm
by Paul
90 working days I have read somewhere!